October 22, 2026
A freight train carries Montgomery County's trash from the Shady Grove Transfer Station to the Resource Recovery Facility in Dickerson. After the waste is burned, the ash goes out by rail to a landfill in Virginia, according to Montgomery Community Media. Not far away, at 21200 Martinsburg Road, the gates of the former GenOn Dickerson Generating Station carry a posted notice about a pending forest conservation plan.
The County is deciding what happens next at both sites. Both decisions are being made in Rockville, using numbers calculated for the whole county. On those countywide numbers the options look nearly the same. In Dickerson they look very different.
The County Council has spent the fall working through what to do with its solid waste over the long term. The Council staff report for the September 15 worksession sets out the choice. One path keeps the Resource Recovery Facility running for decades. The other closes it and sends the waste by truck to landfills outside the county. The Council wants to back one approach by November so the current County Executive and the next one can start the planning, budget, and contract work. Council President Natali Fani-González has set a Thanksgiving goal for that decision. County Executive Marc Elrich has said the Council should take as long as it needs, as Montgomery Community Media reported.
The planning lead time explains the push. The current service agreement with Reworld, the company that runs the facility, expires April 1, 2031, and the County can end it early. According to Council staff, keeping the plant for another 25 years would take a new operating contract plus a major capital project, which is much more than the short-term repairs underway now. At the September 29 session, Reworld described a refurbishment spread over 13 years and said its numbers came in overall probably $100 million below the $356 million Arcadis estimate for a 30-year upgrade. Later in the session, it called a $200 million price the higher side of its estimate for giving the plant 20 to 30 more years.
The Montgomery Community Media account lists four options from the Department of Environmental Protection. The County Executive backs the third.
The County's own cost figures shape most of this decision. A comparison by DEP and Council staff projects that Advanced Waste Processing plus landfilling the leftover waste would cost about the same as upgrading and keeping the incinerator. DEP's projected single-family charges, posted on its Aiming for Zero Waste page, end up almost even:
| Fiscal year | Current system | Advanced Waste Processing plus landfill |
|---|---|---|
| FY28 | $413.75 | $424.27 |
| FY32 | $525.41 | $526.40 |
By FY32, DEP puts the difference for a single-family household at less than $1 a year. The yearly gap is wider in the earlier years, about $10.52 in FY28. Over the long run, though, the household cost comes out close, which puts more weight on the physical changes, and those happen in Dickerson.
How trash gets here. Today the waste comes to Dickerson by rail. At the September 29 session, Reworld argued that keeping rail is better for the environment and the budget than trucking, and it noted how short the Dickerson-to-transfer-station rail link is. If the incinerator closes, the County would truck waste from Shady Grove to out-of-county landfills. DEP officials told Montgomery Community Media that this means 80 loads a day, made by 40 tractor-trailers running two trips each. The Council staff report expects no termination cost on the CSX agreement if waste moves from rail to trucks.
What happens to the site. Under the Executive's proposal, the County would shut the facility down and do "necessary site restoration or remediation work." No future use has been chosen, though the Executive has suggested recycling or solar energy production. His estimated closure costs are $3 million to $6 million to decommission the plant, $1.2 million to clear residual waste, and $1 million for PJM electricity capacity costs.
What happens to food scraps. If the incinerator closes, DEP says the County's existing yard-trim compost facility in Dickerson could take food scraps. If the incinerator stays, food composting would need a different site and an extra $27 million.
All three outcomes affect the same corner of the county, and none of them shows up in the rate table. Whichever way the Council leans, the vote doesn't end it. A closure would mean working out timelines with DEP and the next County Executive. It would also require amending the County's Ten-Year Comprehensive Solid Waste Management Plan, which the Maryland Department of the Environment has to approve. If the Council keeps the plant, planning and design work on a capital project would begin.
The other site is on a slower clock, and so far it hasn't moved. On May 16, 2026, Atmosphere Dickerson Property Owner, LLC applied for a major amendment to the conditional use on the former GenOn property to allow a data center. Its public hearing was set for November 12 and 13, 2026. Bethesda Magazine reported in May that the updated plans showed five buildings on 110 acres. Reported sizes differ. Nature Forward describes 360 megawatts. Bethesda Magazine's July coverage cited about 300 megawatts and roughly 1.1 million square feet, far larger than any of the four data centers the county already has.
Then the rules changed. On July 28, the Council unanimously passed two measures. The first, Zoning Text Amendment 26-01, defines a large data center as one with an aggregate monthly electricity demand, actual or projected, of at least 25 megawatts, and doesn't allow that use in any zone. The second, Expedited Bill 19-26, sets an 18-month moratorium on accepting, reviewing, or issuing building or grading permits for data centers. Councilmember Evan Glass told the room, "Nothing will happen until we answer all the questions our community deserves," Bethesda Magazine reported.
In August, Atmosphere dropped its appeal of the Executive's earlier six-month order, which the Council's action had made moot. A company spokesperson told Bethesda Today it was still weighing its options for the project. The company's lawyers asked for the hearing to be postponed, arguing it would be inefficient to go ahead before the County finishes its rulemaking. The Office of Zoning and Administrative Hearings agreed on September 1 and continued the case through May 16, 2027. The County's hearing page now lists the date as TBD.
The same pattern holds here. The moratorium and the zoning definition are countywide rules, written for every zone in the county. A 1.1-million-square-foot campus has only been proposed for one place, and that place is Dickerson.
For anyone looking at homes here this season, this is what each process looks like at the time of publication:
The county market isn't pushing buyers to rush. In September 2026, Montgomery County had 681 closed sales, down 9.4% from a year earlier, and a median sold price of $610,000, up 1.8%, according to the Greater Capital Area Association of REALTORS. GCAAR also reports that in September 2026 sellers received an average of 97.3% of original list price, the same as September 2025. For the same month, Maryland REALTORS counted 2,447 active listings in the county, up 27.2%, which works out to 3.0 months of inventory, with median days on market holding at 22.
These are countywide figures. Dickerson has so few sales that a single month says little about it on its own. Still, with more inventory and steady days on market across the county, a buyer considering Dickerson this fall can likely follow the November Council action before committing.
Has the County decided to close the Dickerson incinerator? Not as of this week. The Executive has proposed closure, the Council is still in worksessions, and the FY27 budget assumes the plant keeps running through FY27.
Can a data center be built at the old GenOn plant right now? Under ZTA 26-01, large data centers aren't a permitted use in any zone while the Council writes siting rules, and the moratorium stops data center permits from being issued.
Where can I follow these cases? The Council posts its worksession staff reports, DEP keeps its Aiming for Zero Waste page current, and the data center case is on the OZAH hearing page.
This post reports on public proceedings for general information. It isn't legal or financial advice, so please check zoning or contract questions about a specific property with the right professional.